| Concept & Site
Approval achieved |
October 12, 2005 |
| Architectural Design Competition |
January 2006 |
| NBBJ awarded the architectural
bid |
February 2006 |
| Whiting Turner Construction selected as the general contractor |
May 2006 |
| Li Ka Shing Center for Learning and Knowledge2 Study commissioned,
Lane & Alway renovation projects
put on hold. |
July 2006
|
Master site plan study and program verification completed
Connective Elements project phases defined |
August 2006 |
| Site visits |
June & August 2006 |
| Logistics plan available by phase for the execution
of the Connective Elements project |
November 2006 |
| Schematic design phase completed for the Li Ka Shing Center for Learning and Knowledge |
December 2006 |
| Schematic and detailed
design and construction documents completed for Phases 0 & 1A
of the Connective Elements project. |
January 2007 |
| Schematic & detailed design completed for the Docks & Tunnel
phase of the Connective Elements project |
January 2007 |
Seek Board of Trustuees approval as follows:
• Design Approval: Li Ka Shing Center for Learning and Knowledge
• Design approval: Landscape and Sitework
• Project approval:Phases 0 and 1A utilities
|
February 12, 2007 |
| Begin the detailed design phase for the Li Ka Shing Center for Learning and Knowledge |
March 2007 |
Seek Board of Trustees approval as follows:
• Construction
approval: Phases 0 & 1A utilities
•
Design
approval: Dock & Tunnel |
April 23, 2007 |
| Close general “A” permit parking
lot south of Fairchild, Beckman and CCSR. Re-stripe for
disabled, metered, “A” carpool and loading and
unloading only |
April 24, 2007 |
| Start construction on phases 0 and 1A Utilities |
April 30 2007 |
| Seek construction approval from the Board of
Trustees for the Dock and Tunnel phases |
June 2007 |
| Start construction on the Dock and Tunnel |
August 2007 |
| Demolish Fairchild Auditorium |
October 2007 |
| Complete Phases 0 & 1A |
October 2007 |
Seek construction approval from the Board
of Trustees for the Li Ka Shing Center for Learning and Knowledge |
December 2007 |
| Complete the Loading Dock & Tunnel |
May 2008 |
| Open the Loading Dock for Receiving and Delivery |
August 2008 |
| Achieve Temporary Occupancy of the Li Ka Shing Center for Learning and Knowledge |
December 2009 |
| Commission and formally open the Li Ka Shing Center for Learning and Knowledge |
March 2010 |