Advanced Notice of Construction - 7/25-8/1
Posted 05:23 PM, July 25, 2008, by madaca
I am sorry to send such a belated update to the two weeks of construction, July 21st through August 1st. Some of this work you will have seen take place this week. I am only including the two largest projects in this update but will catch everyone up on the works when I get back from vacation. I will also try to get some new pictures up during August. Hope all is going well for you!
LKSC
As you probably noticed the slab was poured on July 14th - this is a big milestone which has enabled us to move forward to an even bigger milestone - the erection of the steel.
Additionally, the webcam is fun to watch right now because the building is changing visibly daily. Just go to http://lksc.stanford.edu/ and click on the two webcam bullets to enlarge the image and/or control it.
- Install rebar to mechanical room walls
- Spray the shotcrete mechancial room walls
- Prep and place rebar for mechanical room slab on grade (this is the only large piece of the slab left to pour - over by the northwest corner of Beckman)
- Pour mechanical room slab on grade
- Begin forming mechanical room roof - the mechanical room is a one story underground structure attached to the building but the area does not carry up through the other floors.
- Install rebar to the new LKSC tunnel roof
- Pour the new LKSC tunnel roof
- Install waterproofing on tunnel roof
- Begin steel erection at 1st floor
- Begin 2nd floor steel erection
SIM1
Right now it is all about digging a really big hole, getting rid of lots! of dirt and shoring up the remaining dirt.
July 21th - 25th
- Excavate to 15' below grade and continue to install temporary shoring
July 28th - August 1st
- Excavate to 20' below grade and continue to install temporary shoring
- Install Sacrificial Ground Anchors