Project Update
Posted 10:23 AM, December 15, 2008, by jknapp1
LKSC Building
GFRC and precast Skin erection
Roofing at high and low roofs
Exterior Framing System
Interior Framing at 2nd and 3rd Floors
Priority Wall Framing at 4th Floor
MEP Rough-in at all floors
LKSC Sitework
Underground Utilities at North Side of LKSC Building
Beckman Tunnel Roof Waterproofing
SIM 1
Forming of basement walls are in progress an scheduled to be complete by December 12th
Erection of steel columns and steel beams from the basement floor to 2nd floor is scheduled to begin December 8th; work will continue through the month of December 2008
Campus Drive Realignment
The following work will be ongoing the weeks of 12/1/, 12/8, & 12/15 for the Campus Drive Realignment Project:
Week of 12/1
Install walls and lid rebar in steam vault W5
Install first pieces of concrete steam tunnel in Welch Rd
Final excavation for steam vault W1 slab
Week of 12/8
Install concrete steam tunnel along Welch Rd
Set and pour slab for steam vault W1
Pour concrete for walls and lid of steam vault W5
Week of 12/15
Strip formwork of steam vault W5
Lay chilled water line around steam vault W5
Install walls and lid rebar in steam vault W1
Loading/Receiving Dock
The Loading dock, Receiving Area and Tunnel are nearly complete
Floors are currently being sealed and burnished
Final cleaning is scheduled during the next two weeks
Final approvals for all MEP systems and Life Safety systems are being pursued
WT is preparing for the final punch walk on December 10th, 2008
RAF Ramp Relocation
The new ramp portion of the project is nearly complete
Final installation of handrail and all touch up painting will be performed during the next two weeks
Work for the LKSC Entry Bridge portion of the project is scheduled to begin during the early part of February, 2009